Key Dates
October 2022 → April 2023
Phase 1 - Septic System Replacement (completed early 2023)
Work was completed early 2023.
October 2023 → April 2024
Phase 2a - Pathways & Accessibility (completed January 2024)
Pathway work will commence with short notice (October 24th) in an effort to complete paving work prior to 2023 winter shutdown. (completed January 2024)
March → April 2024
Phase 2b- Irrigation & Landscape Upgrades
Irrigation system and landscape upgrades are scheduled to be completed spring of 2024.
March → April 2024
Phase 3 - Lakeshore Enhancements
This phase involves the removal of non-native soil material from the lakeshore to create a more user friendly and natural shoreline.